Kabelquerschnitt für 225 Ampere bei 70 Meter (400V)

Berechnung des erforderlichen Leiterquerschnitts (mm²) und des Spannungsfalls nach DIN VDE 0100-520 / IEC 60364 für 225 A über 70 m einfache Leitungslänge bei 400V.

Copper Cable (≤3% Drop)95 mm²Drop: 6.15V (1.54%)
Aluminum Cable (≤3% Drop)150 mm²Drop: 6.42V (1.6%)
Voltage at Load393.9 VLine Loss: 2394.8 W
Max Power & Breaker155.88 kW225A MCB/MCCB

IEC 60364 Cable Cross-Section Table (1.5 mm² – 400 mm²) for 225A at 70m

Cross-Section (mm²)Cu AmpacityAl Ampacity Cu Voltage DropLoad VoltageAl Voltage DropPower LossStatus
1.5 mm²16 A12 A389.19 V (97.3%)10.8 V641.98 V (160.5%)151672.5 WDrop High
2.5 mm²24 A18 A233.52 V (58.38%)166.5 V385.19 V (96.3%)91003.5 WDrop High
4 mm²32 A25 A145.95 V (36.49%)254.1 V240.74 V (60.19%)56877.2 WDrop High
6 mm²41 A32 A97.3 V (24.32%)302.7 V160.5 V (40.12%)37918.1 WDrop High
10 mm²57 A44 A58.38 V (14.59%)341.6 V96.3 V (24.07%)22750.9 WDrop High
16 mm²76 A59 A36.49 V (9.12%)363.5 V60.19 V (15.05%)14219.3 WDrop High
25 mm²101 A78 A23.35 V (5.84%)376.6 V38.52 V (9.63%)9100.4 WDrop High
35 mm²125 A97 A16.68 V (4.17%)383.3 V27.51 V (6.88%)6500.2 WDrop High
50 mm²151 A118 A11.68 V (2.92%)388.3 V19.26 V (4.81%)4550.2 WDrop High
70 mm²192 A150 A8.34 V (2.08%)391.7 V13.76 V (3.44%)3250.1 WDrop High
95 mm²232 A181 A6.15 V (1.54%)393.9 V10.14 V (2.53%)2394.8 W✓ OK (≤3%)
120 mm²269 A210 A4.86 V (1.22%)395.1 V8.02 V (2.01%)1895.9 W✓ OK (≤3%)
150 mm²309 A241 A3.89 V (0.97%)396.1 V6.42 V (1.6%)1516.7 W✓ OK (≤3%)
185 mm²353 A275 A3.16 V (0.79%)396.8 V5.21 V (1.3%)1229.8 W✓ OK (≤3%)
240 mm²415 A324 A2.43 V (0.61%)397.6 V4.01 V (1.0%)948.0 W✓ OK (≤3%)
300 mm²477 A372 A1.95 V (0.49%)398.1 V3.21 V (0.8%)758.4 W✓ OK (≤3%)
400 mm²570 A445 A1.46 V (0.36%)398.5 V2.41 V (0.6%)568.8 W✓ OK (≤3%)

FAQ — Kabelquerschnitt für 225 Ampere bei 70 Meter (400V)

Welcher Kabelquerschnitt wird für 225A bei 70m (400V) benötigt?

Für 225 Ampere über 70 Meter bei 400V wird ein Kupferkabel von 95 mm² empfohlen, um den Spannungsfall unter 3% (6.15V bzw. 1.54%) zu halten.

Wie hoch ist die maximale Leistung bei 225A und 400V?

Die übertragbare Leistung beträgt 155.88 kW bei einer empfohlenen Absicherung von 225A.